Karen, the project sponsor, is not happy with the team's progress based on their current rate of work. She believes that the WIP limit is at fault and demand that the limit be removed so that the team can take on more work to get the product completed faster. What do you tell Karen?
A You tell Karen you will remove the WIP limit and encourage the team to work as best as they can.
B You inform Karen that you will have the team work overtime.
C You tell Karen you will hire additional staff.
D You tell Karen that WIP limits are meant to keep the team focused.