Questions: Exam 2 Question 44 of 50 This test 60 point(s) possible This question 1 point(s) possible Project A Project B Time 0 -10,000 -10,000 Time 1 5,000 4,000 Time 2 4,000 3,000 Time 3 3,000 10,000 If WiseGuy inc is choosing one of the above mutually exclusive projects (Project A or Project B), given a discount rate of 9%, which should the company choose? A. Project A B. Project B C. Neither project - both have negative NPV. D. Both projects - both have positive NPV.

Exam 2
Question 44 of 50
This test 60 point(s) possible
This question 1 point(s) possible

Project A  Project B 
Time 0  -10,000  -10,000 
Time 1  5,000  4,000 
Time 2  4,000  3,000 
Time 3  3,000  10,000

If WiseGuy inc is choosing one of the above mutually exclusive projects (Project A or Project B), given a discount rate of 9%, which should the company choose?

A. Project A
B. Project B
C. Neither project - both have negative NPV.
D. Both projects - both have positive NPV.
Transcript text: Exam 2 Question 44 of 50 This test 60 point(s) possible This question 1 point(s) possible \begin{tabular}{ccc} & Project A & Project B \\ Time 0 & $-10,000$ & $-10,000$ \\ Time 1 & 5,000 & 4,000 \\ Time 2 & 4,000 & 3,000 \\ Time 3 & 3,000 & 10,000 \end{tabular} If WiseGuy inc is choosing one of the above mutually exclusive projects (Project A or Project B), given a discount rate of $9 \%$, which should the company choose? O A. Project A O B. Project B O C. Neither project - both have negative NPV. O D. Both projects - both have positive NPV.
failed

Solution

failed
failed

To determine which project WiseGuy Inc should choose, we need to calculate the Net Present Value (NPV) of each project using the given discount rate of 9%. The NPV is calculated using the formula:

\[ NPV = \sum \frac{C_t}{(1 + r)^t} - C_0 \]

where \(C_t\) is the cash flow at time \(t\), \(r\) is the discount rate, and \(C_0\) is the initial investment.

Calculating NPV for Project A:

  • Time 0: Cash flow = -10,000
  • Time 1: Cash flow = 5,000
  • Time 2: Cash flow = 4,000
  • Time 3: Cash flow = 3,000

\[ NPV_A = \frac{5,000}{(1 + 0.09)^1} + \frac{4,000}{(1 + 0.09)^2} + \frac{3,000}{(1 + 0.09)^3} - 10,000 \]

\[ NPV_A = \frac{5,000}{1.09} + \frac{4,000}{1.1881} + \frac{3,000}{1.295029} - 10,000 \]

\[ NPV_A = 4,587.16 + 3,367.86 + 2,316.99 - 10,000 \]

\[ NPV_A = 10,271.99 - 10,000 = 271.99 \]

Calculating NPV for Project B:

  • Time 0: Cash flow = -10,000
  • Time 1: Cash flow = 4,000
  • Time 2: Cash flow = 3,000
  • Time 3: Cash flow = 10,000

\[ NPV_B = \frac{4,000}{(1 + 0.09)^1} + \frac{3,000}{(1 + 0.09)^2} + \frac{10,000}{(1 + 0.09)^3} - 10,000 \]

\[ NPV_B = \frac{4,000}{1.09} + \frac{3,000}{1.1881} + \frac{10,000}{1.295029} - 10,000 \]

\[ NPV_B = 3,669.72 + 2,526.00 + 7,720.68 - 10,000 \]

\[ NPV_B = 13,916.40 - 10,000 = 3,916.40 \]

Conclusion:

  • NPV of Project A = 271.99
  • NPV of Project B = 3,916.40

Both projects have positive NPVs, but Project B has a higher NPV than Project A. Therefore, WiseGuy Inc should choose Project B.

The answer is B: Project B.

Explanation of Options:

A. Project A - Incorrect, as Project B has a higher NPV. B. Project B - Correct, as it has the highest NPV. C. Neither project - both have negative NPV - Incorrect, as both projects have positive NPVs. D. Both projects - both have positive NPV - Incorrect, as only one project can be chosen, and Project B is the better choice.

Was this solution helpful?
failed
Unhelpful
failed
Helpful