Questions: Why would a project manager look specifically at the rows of a responsibility assignment matrix? a to see how long each project activity would take b to see everyone who would be involved in a specific part of a project c to see what role(s) a specific person will play on a project d to see how much money has been allocated for each project role

Why would a project manager look specifically at the rows of a responsibility assignment matrix?
a to see how long each project activity would take
b to see everyone who would be involved in a specific part of a project
c to see what role(s) a specific person will play on a project
d to see how much money has been allocated for each project role
Transcript text: Why would a project manager look specifically at the rows of a responsibility assignment matrix? a to see how long each project activity would take b to see everyone who would be involved in a specific part of a project c to see what role(s) a specific person will play on a project d to see how much money has been allocated for each project role
failed

Solution

failed
failed
Answer

The answer is c to see what role(s) a specific person will play on a project

Explanation
Option 1: to see how long each project activity would take

This option is incorrect because the responsibility assignment matrix (RAM) is not used to determine the duration of project activities. Instead, it is used to assign roles and responsibilities.

Option 2: to see everyone who would be involved in a specific part of a project

This option is partially correct but not the best answer. While the RAM can show who is involved in specific parts of the project, it is more specifically used to identify the roles and responsibilities of individuals.

Option 3: to see what role(s) a specific person will play on a project

This is the correct answer. The primary purpose of a responsibility assignment matrix is to outline what roles and responsibilities each team member has in the project. It helps in clarifying who is responsible for what tasks.

Option 4: to see how much money has been allocated for each project role

This option is incorrect because the RAM does not deal with financial allocations. Budgeting and financial planning are typically handled through other project management tools and documents.