Questions: Which of the following constraints must be balanced to ensure effective project management?
I. stakeholders
II. quality
III. scope
a and II
b II and III I and III
Transcript text: Which of the following constraints must be balanced to ensure effective project management?
I. stakeholders
II. quality
III. scope
a and II
b II and III I and III
Solution
The answer is b: II and III.
Explanation for each option:
I. Stakeholders: While stakeholders are important in project management, they are not typically considered a constraint. Instead, they are entities that have an interest in the project and can influence its outcome.
II. Quality: Quality is indeed a constraint in project management. It refers to the standards and criteria that the project must meet, and it needs to be balanced with other constraints to ensure the project is successful.
III. Scope: Scope is another key constraint in project management. It defines what is included in the project and what is not, and it must be managed carefully to ensure the project stays on track.
Therefore, the constraints that must be balanced to ensure effective project management are quality (II) and scope (III).