Transcript text: 40-A contractor wants to install a valve and actuator on a sulfuric acid line. The contractor ha had the plant's safety training and has the correct PPE, but the safety showers are not working because a mechanical contractor is doing repairs. What should the technician instruct the contractor to do?
- Proceed since the contractor has PPE and training.
- Proceed with caution and be sure to have another worker nearby with a bucket.
- Do not proceed until after lunch when the showers should be fixed.
- Do not proceed until safety showers are verified working.