Questions: During which phase does a project manager monitor the work performed to create a deliverable? Phase 3 Phase 2 Phase 1 Phase 4

During which phase does a project manager monitor the work performed to create a deliverable? Phase 3 Phase 2 Phase 1 Phase 4
Transcript text: Strayer | Login MILESTONE $4 \mid$ Project Manas Busines app.sophia.org/spcc/project-management-2-milestone-4-1/11 1. UNIT 4 - MILESTONE 4 1 2 3 4 5 6 7 Question 11 Mark this question During which phase does a project manager monitor the work performed to create a deliverable? Phase 3 Phase 2 Phase 1 Phase 4 SAVE \& CONTINUE Report an issue with this question
failed

Solution

failed
failed
Answer

The answer is Phase 4.

Explanation
Option 1: Phase 3

Phase 3 typically involves the execution of the project plan, where the project team carries out the tasks necessary to create the deliverables. While some monitoring occurs, it is not the primary focus of this phase.

Option 2: Phase 2

Phase 2 often involves planning, where the project manager develops detailed plans for how the project will be executed, monitored, and controlled. Monitoring is planned here but not actively performed.

Option 3: Phase 1

Phase 1 is usually the initiation phase, where the project is defined and authorized. Monitoring is not a focus at this stage.

Option 4: Phase 4

Phase 4 is the monitoring and controlling phase. During this phase, the project manager actively monitors the work being performed to ensure it aligns with the project plan and makes necessary adjustments to keep the project on track. This phase is crucial for ensuring that the deliverables meet the required standards and are completed on time and within budget.

Was this solution helpful?